You should be aware of the following limitations if you're using the work breakdown structure in Project Operations. These limits apply to projects and tasks.
Project limitations
Field | Limits |
---|---|
Maximum total tasks for a project | 3,000 |
Maximum total duration for a project | 5,475 days (15 years) |
Maximum total resources for a project | 1000 |
Maximum total links (successor only) for a project | 600 |
Maximum total custom fields for a project | 10 |
Maximum checklist items per task | 20 |
Task limitations
Field | Limits |
---|---|
Maximum hierarchy level | 10 levels |
Maximum links (successor + predecessor) | 20 |
Maximum duration of leaf task | 1,250 days |
Maximum duration of a summary task | 5,475 days (15 years) |
Maximum resources assigned to a task | 50 resources |
Supported date range for a task | 1/1/2000 - 12/31/2149 |